Birchwood Flooring Project
Last Update: March 26, 2026
The Park District is in the process of renovating the flooring at Birchwood Recreation Center, view the plan HERE.
The new flooring will be installed throughout most of the facility, except for the gymnasium, locker rooms, and dance room located on the lower level. This upgrade will improve the overall aesthetic of the center and offer a more durable surface for walking and activities.
Project timeline
- Design Phase: January to March
- Public Bidding Phase: Early March
- Construction Phase:
- Lower-Level August 10th to August 20th
- Upper-Level September 8th to September 11th
PHGC 18th Green Renovation Project
Last Update: March 26, 2026
The Park District is undertaking renovations to the 18th green at Palatine Hills to enhance the playability of the approach area and the overall surface of the green. The project involves relocating the sand trap to the west, positioning it along the southern edge of the green to help reduce the number of balls rolling into the creek. Additionally, the green will be reshaped and leveled to accommodate more pin placements on the green. The green will remain in its current location. Since the sand trap is situated within the floodplain, a permit from the Metropolitan Water Reclamation District (MWRD) is required, which is anticipated to extend the permit approval process by approximately six to seven months. As a result, staff have decided to reschedule the construction phase of the project to August 2027 to better align with turf establishment schedules.
Project Timeline
- Design Phase: January to April
- Permitting Phase: April to November
- Public Bidding Phase: Late April
- Construction Phase: August 2027 to September 2027
Paving Projects
Last Update: March 26, 2026
The paving projects scheduled for 2026 include Phase 2 of the Falcon Recreation Center pavement renovation and a segment of the Palatine Trail between the bridge at Ashwood Park and Smith Road. Phase 2 of the Falcon Recreation Center renovation will primarily focus on enhancing accessibility features around the facility, including the designated ADA parking areas. The Palatine Trail renovation will involve removing the existing asphalt and replacing it in the same location, except for a small section between Hawk Street and Smith Road (behind Saint Joseph Home). In this area, the trail will be relocated approximately 20 to 30 feet northward, away from the property boundaries.
View the Paving Project Plan HERE
Project Timeline
- Design Phase: January to April 1st.
- Public Bidding Phase: Mid-April.
- Construction Phase: Late August.
Admin Center
Last Update: March 26, 2026
The Park District is relocating all administrative functions from the Community Center to the new facility at 150 W. Wilson Street to increase programming space at the Community Center. This new facility was acquired through an Inter-Governmental Agreement with the Village of Palatine, which is projected to save taxpayers millions of dollars over the next five to six years. Both agencies required expanded facilities to better serve the public.
View the Admin Center Plans HERE
Project Timeline
- Design Phase: November 2025 to March 16th.
- Public Bidding Phase: March 23rd to April 15th.
- Construction Phase: August to January
Wally Degner Park Playground Replacement
Last Update: October 13, 2025 –
Design is finalized with playground removal and construction later this year.
Thank you to everyone for their input.
See the winning results on the Playground Projects page.
The Grove – New Playground
Last Update: October 13, 2025 –
Design is finalized and construction will begin later this year.
Thank you to everyone for their input.
See the winning results on the Playground Projects page.
Cedar Park Playground
Last Update: October 30, 2024 –
Cedar Park playground will be closed starting Wednesday 9/18 for removal and replacement.
Playground open for use as of 10/19
Celtic Park – Artificial Turf Replacement
Last Update: September 19, 2024 –
Project started on Friday July 12th.
All turf covering has been removed.
The Contractor will start fine grading the subbase before installing the new turf.
Palatine Trail Update
Last Update: April 23, 2024 –
Palatine Trail along Illinois Avenue was successfully updated.
Eagle Park Playground
Last Update: February 8, 2024 –
Eagle Park Playground has been completely renovated and is open for play! Special thanks to Kids Around The World for their removal and recycling of the previous playground.
Birchwood Recreation Center Elevator
Last Update: January 3, 2024 –
Birchwood Recreation Center Elevator project has concluded. Operations have resumed as normal.
Hamilton North Parking Lot
Last Update: April 23, 2024 –
Hamilton North Parking Lot has been completed.
Community Center Gym Floor
Last Update: January 3, 2024 –
Community Center Gym Floor has completely resurfaced, repainted, and refinished. It now features basketball courts, volleyball courts, and pickleball courts. New bleachers and gym divider has been added as well.
Meadowlark Renovation Plans
Last Update: October 13, 2025 –
Phase One plans for Meadowlark Park
Meadowlark Playground open as of 10/28
Construction still in progress.
Osage Park Playground
Last Update: January 3, 2024 –
Osage Park Playground has been completely renovated and is open for play! Special thanks to Kids Around The World for their removal and recycling of the previous playground.
Palatine Trail Repaving
Last Update: January 3, 2024 –
Palatine Trail Repaving along Dundee Rd and near Dutch Schultz Park has concluded. Trail is open!